Define
Is the opportunity technically and commercially viable?
Project charter · site criteria · constraints · risk register · execution premise
Six decision gates
Is the opportunity technically and commercially viable?
Project charter · site criteria · constraints · risk register · execution premise
Is the scope mature enough for investment approval?
Feasibility · pre-FEED · basis of design · Class 4/3 estimate · Level 2/3 schedule
Can procurement and construction execute without unresolved interfaces?
FEED · specifications · calculations · drawings · quantities · constructability reviews
Do equipment and contracts meet technical, commercial and schedule requirements?
RFQs · bid tabs · purchase orders · vendor data · inspection · expediting · logistics
Is field progress safe, compliant and tied to the approved baseline?
Work packages · field engineering · QA/QC · HSE · cost/schedule control · completions
Is each system ready for safe energization, startup and performance testing?
Turnover dossiers · pre-commissioning · SAT · startup · performance verification · training
Integrated controls
Controls are designed before execution starts and scaled to the size, contract model and risk of the mandate.
Decision rights, approval matrix, stage gates, delegated authority and reporting calendar.
WBS, battery limits, scope register, interface register, deliverable ownership and change traceability.
Control budget, coding structure, integrated master schedule, progress rules, forecast and variance analysis.
Quantified exposure, named owners, mitigation dates, trend management and approved change control.
Inspection and test plans, surveillance, NCR closure, safe work systems and leading indicators.
Document control, model coordination, vendor data, submittals, RFIs, turnover records and as-built status.
Contracting strategy
The contract structure should match scope maturity, market capacity, owner capability, financing requirements and the interfaces the owner is prepared to retain.
Independent technical, commercial and delivery oversight from project definition through acceptance.
Integrated engineering, procurement and construction management with transparent owner control of packages and contracts.
Single-point delivery responsibility for defined facilities, systems or work packages with agreed performance obligations.
Governance, schedule, cost, risk, change, quality, information and interface control across multiple contractors.